New Wing Construction Progress

Construction of the new wing is scheduled to be completed by the end of December, 2020.  Follow the progress and watch our new wing come to life!

July 2020

Stakes identifying the boundaries of the new wing.

July 2020

The preparation of the site begins.

July 2020

The foundation block for the new wing.

July 2020

Drain pipes for the new wing.

August 2020

Preparing the foundation for concrete to be poured.

August 2020

The concrete foundation for the new wing.

August 2020

The framing for one of the side walls.

August 2020

The interior wall frames for one of the classrooms in the new wing.

August 2020

The framing for the exterior walls and most of the interior walls is complete.

August 2020

The truss work is almost complete!

August 2020

The first layer of the roof is installed.  The new wing is starting to take shape!

September 2020

The drywall work has begun!

October 2020

The tilework on the walls of the new restrooms is complete.

October 2020

The drywall work and installation of the sprinkler system is almost complete.

October 2020

The overhang over the back entrance is installed.

October 2020

The walls of the classrooms and offices are painted.

October 2020

The flooring throughout the new wing is in the process of being laid.

October 2020

The opening in the main hallway of the new wing.  Windows flank either side, close to the roofline, letting in lots of sunshine.

October 2020

The windows have arrived! 

October 2020

A classroom is nearing completion.

October 2020

The exterior heating and cooling units are placed and connected...just in time for chilly temperatures.

Image

There are no resources or collections to display